Gas Midstream Services

 

Planned Outage
June 12, 2009
Willow Run Outage Lifted

All work at the Willow station will be completed today. As a result, the Willow outage will be lifted effective tomorrow, Gas Day June 13... 

ANR Willow Run Receipt Point (Map 9038) and the associated Willow Run Pool (Map 9307).

All work at the Willow station will be completed today. As a result, the Willow outage will be lifted effective tomorrow, Gas Day June 13. Thank you all very much for your excellent cooperation during the outage.

Finally, please remember that MichCon will not accept intra-day nom increases at Willow for Gas Day June 12. This restriction will also be lifted effective with tomorrow's Gas Day of June 13.

If you have questions, please contact Kelly Naragon at 313-235-1036 or Cindy Reppke at 313-235-1037. Thank you again.

Planned Outage
May 22, 2009
Willow Run Outage Notice - Revised 5/21/09

The ANR Willow Run station will be shut in for a scheduled outage from June 8 through June 12, 2009 due to construction work...

As a reminder, the ANR Willow Run station will be shut in for a scheduled outage from June 8 through June 12, 2009 due to construction work. As a result of the shut-in, all interruptible services, including those associated with interruptible secondary points, will be prohibited from utilizing the ANR Willow Run Receipt Point (Map 9038) and the associated Willow Run Pool (Map 9307) during the outage period.

MichCon is also reminding End User Transportation customers and all transportation and storage customers with MichCon Generic firm receipt points that utilization of any specific Generic receipt point is subject to availability. As such MichCon strongly encourages these customers to refrain from using the ANR Willow Run Receipt Point (Map 9038) and the associated Willow Run Pool (Map 9307) during the outage. MichCon requests these customers to coordinate with their suppliers to eliminate or minimize usage of the ANR Willow Run Receipt Point (Map 9038) and associated Willow Run Pool (Map 9307) during the outage period. Such action will mitigate the need for MichCon to make mandatory cuts with little or no notice to its shippers.

Please be advised that during the outage period, MichCon will not accept any Timely Cycle nominations submitted after the 2:00 p.m. window close. Additionally, during this timeframe, MichCon will not accept any intraday nomination increases at the ANR Willow Run Receipt Point (Map 9038) or the associated Willow Run Pool (Map 9307).

We will continue to send reminders of the upcoming outage. If you have questions, please contact Tom Budzyn at 313-235-1040 or Kelly Naragon at 313-235-1036. Thank you for your cooperation during this outage.

Planned Outage
May 18, 2009
Willow Shut in Notice - June 8 - 12, 2009

The ANR Willow station will be shut in for a scheduled outage from June 8 through June 12, 2009 due to construction work...

As a reminder, the ANR Willow station will be shut in for a scheduled outage from June 8 through June 12, 2009 due to construction work. As a result of the shut-in, all interruptible services, including those associated with interruptible secondary points, will be prohibited from utilizing the ANR Willow Map 9038 receipt point during the outage period.

MichCon is also reminding End User Transportation customers and all transportation and storage customers with MichCon Generic firm receipt points that utilization of any specific Generic receipt point is subject to availability. As such MichCon strongly encourages these customers to refrain from using the ANR Willow Map 9038 receipt point during the outage. MichCon requests these customers to coordinate with their suppliers to eliminate or minimize usage of the ANR Willow Map 9038 receipt point during the outage period. Such action will mitigate the need for MichCon to make mandatory cuts with little or no notice to its shippers.

Please be advised that during the outage period, MichCon will not accept any nominations submitted after the timely 2:00 p.m. window close. Additionally, during this timeframe, MichCon will not accept any intraday nominations at the ANR Willow Map 9038 receipt point.

We will continue to send reminders of the upcoming outage. If you have questions, please contact Tom Budzyn at 313-235-1040 or Kelly Naragon at 313-235-1036. Thank you for your cooperation during this outage.

Planned Outage
April 22, 2009
Scheduled Outage at ANR Willow - June 8 - 12, 2009

Please be advised that the ANR Willow station will be shut in for a scheduled outage from June 8 through June 12, 2009 due to construction work...

Please be advised that the ANR Willow station will be shut in for a scheduled outage from June 8 through June 12, 2009 due to construction work. As a result of the Willow station shut-in, MichCon anticipates that it will curtail all interruptible services, including those associated with interruptible secondary points, at the ANR Willow Map 9038 between June 8 and June 12, 2009. Should these plans change, we will notify our shippers as quickly as possible. Currently, MichCon does not know whether firm services will be affected during the scheduled outage; however, such action may be necessary.

We will continue to send reminders of the upcoming outage, and also keep you apprised as more information becomes available. Thank you for your assistance during this period.

Customer Activity Website
User Name
Password
You must be an authorized user to access this private network

Smart pigging maintenance operation